JEA is powerless to speed up the timeline for when the expansion at the Plant Vogtle nuclear facility will come on board.
Tuesday morning, its board of directors received an update on the project outside of Waynesboro, Georgia. During that conversation, it was noted delays on the project are costing the utility $150 million annually.
Board member Joe DiSalvo noted there are 162 Inspections, Tests, Analyses and Acceptance criteria that must be completed to Nuclear Regulator Commission satisfaction…